Today is the big day. All connections are made, so the boiler can be filled, both with water and pellets and then it can be started!
We filled the floor heating and warm water system with water and got 4 bags of 15 kilo of 6 mm pellets and put them in the pellet silo. We did not fill the radiator system as I still need to put gyprock behind them, which is way easier when the radiator is off the wall.
The the big moment, turning on the pumps and turning on the boiler. Testing, Loading, Igniting, Pre-burn and then burning. The display showed nicely in what stage the heater is.
We found out the expansion tank of the warm water system needed more air pressure, but after that was fixed, all was good!